QUESTION:
I want to build a cottage extremely from foam blocks. There are some questions.
Than will advise to revet? A bar? Plaster? Heard, that not breathing walls from foam concrete can cause dampness in the house. What minimal thickness to make walls that it was warm? The minimal density for a house in 2-3 floors.
THE ANSWER:
Can revet everything. Foam concrete does not cause dampness in the house.
All depends on density of mark foamconcrete, the warmest - 400 (but it is used only as partitions). The minimal density for a house of 600 kg / m3.
QUESTION:
How many there is ?utting technics for foam isol?
What amount of forms is necessary for continuous process their cost?
THE ANSWER:
Cutting a framework for foam isol- 150 hrn.
Cost of the form 1?1?1 - 790 hrn.
Cost of the form 1?1?1,5 - 890 hrn.
Forms 6-7 pieces are necessary
QUESTION:
Question on practical application of your equipment. That will be, if the compressor provides pressure of 8 kg / sm2, but productivity only 200-250 ?/minutes. The volume of release or manufacturing foam isol will simply decrease at such parameters of the compressor it is impossible basically? The question interests in connection with a problem of minimization large-sized parameters of the equipment for operating conditions on a building site.
THE ANSWER:
According to the technical rules, for reception of a qualitative material the compressor should have such parameters: 6 atm. - 500 l/minutes.
QUESTION:
We plan pass a factory on manufacture of foam concrete. It is necessary 80 cube. In change (8 hour.). Purchase will cost what cost at you equipment (shipment at own expense) and what completeness of this equipment for us. Forms under Cut+ Cutting the machine.
THE ANSWER:
Cost of the equipment 42800 hrn. Into the complete set of installation enters: concrete mixer, foam generator, the compressor. The cutting machine 35800 hrn. Cassette forms on 1,5 m3 for blocks 600?300?200 - 4600 hrn., under condition of the order over six forms the price 3900 hrn. + the additional equipment
QUESTION:
Tell, please, the room in which the equipment for manufacture of foam concrete will be established, productivity approximately 10 m3 / hour should answer what requirements: